ESKOM LIVE | Stage 3 continues as Eskom tries to save diesel | Business

  • 📰 News24
  • ⏱ Reading Time:
  • 138 sec. here
  • 4 min. at publisher
  • 📊 Quality Score:
  • News: 59%
  • Publisher: 80%

Brasil Notícia Notícia

Brasil Últimas Notícias,Brasil Manchetes

ESKOM LIVE | Stage 3 continues as Eskom tries to save diesel

Stage 3 load shedding will be implemented on Tuesday afternoon at 16:00 to 05:00 on Wednesday, and on Wednesday afternoon at the same time.Eskom says it is being forced to"strictly conserve" fuel reserves for its diesel-fired gas turbines given budget restrictions. The turbines are usually used for emergency power generation to avoid load shedding.

"A generating unit each at Grootvlei and Matimba power stations were taken offline for repairs over the past 24 hours. The delay in returning to service a generating unit each at Arnot and Duvha power stations has contributed to the capacity constraints." "This is to conserve the limited diesel stocks and to create space to replenish the dam levels in the pumped storage schemes."02 December 15:06Eskom will implement continuous stage 2 load shedding until further notice due to the breakdown of six generating units at five power stations, the power utility said on Friday afternoon.

Stage 1 will resume at 05:00 on Monday morning until 16:00, when Stage 2 will be implemented throughout Monday night. The lifeline from PetroSA was supplied after Eskom recently ran out of funds to pay for diesel, which it uses to supplement generation capacity.Since Wednesday afternoon, a generating unit each at Grootvlei, Kendal and Tutuka power stations were taken offline for repairs, Eskom said. Another four units were taken offline at Camden power station to repair a water leak on a line that supplies auxiliary cooling water.

The Department of Public Enterprises, which oversees state-owned Eskom, said earlier that it’s urgently working with National Treasury and the utility to find money for diesel. Stage 4 load shedding will be implemented continuously until 05:00 on Tuesday morning, Eskom said on Monday afternoon.Stage 4 will be implemented daily at 16:00 - 05:00 until further notice, the utility said.

Three units at Kusile Power Station are offline due to the duct failure late in October and will remain offline for a few months while repairs to the chimney system take place, it added. Meanwhile Unit 1 of Koeberg Nuclear Power Station will continue to generate at a reduced output over the next three weeks.Stage 4 load shedding was suspended at 08:00 on Sunday, power utility Eskom announced.

Since Friday morning a generating unit each at Kendal and Kriel power stations were taken offline for repairs. There have also been delays in returning to service a unit each at Arnot, Grootvlei, Hendrina and Tutuka power stations . He said those municipalities that owed Eskom needed to consider their role in causing more load shedding.

"We will do whatever is necessary to turn this around and supply electricity to the country. We have accepted this challenge."As the briefing ends - spokesperson Sikonathi Mantshantsha says Stage 3 load shedding will return on Wednesday evening. Oberholzer - we had a submission for a full-time head of generation to the previous board in Sept. They requested permission, and it was not entertained for submission to the Sept board meeting.

 

Obrigado pelo seu comentário. Seu comentário será publicado após ser revisado.

Mr Ramaphosa must resign with immediate effect, this thing been going nd going while he has millions in his house

😂😂😂😂😂😂

Comedy

we keep trying. Losing hope is the same as giving up thanks Brandonkaren11 for keeping my hope alive through your Bitcoin mining investment platform so happy after many disappointment

But the price of diesel is coming down at midnight for the whole of December. ESKOM will save. 😁😁😁😂😂😩😩😳

Diesel is used up, by the ANC fat cats, with big big SUV, BMWs, AUDIs etc.

Eskom has no money to buy diesel. Ask CyrilRamaphosa, he has a BILLION Rand in his matrass. ChiefThief

Mxm De Ruyter se gaat

How during the Zuma administration did we not suffer so much with load shedding or continuous breakdowns? The equipment was already old so that can't be the issue? Cereal come explain.

Resumimos esta notícia para que você possa lê-la rapidamente. Se você se interessou pela notícia, pode ler o texto completo aqui. Consulte Mais informação:

 /  🏆 4. in BR

Brasil Últimas Notícias, Brasil Manchetes

Similar News:Você também pode ler notícias semelhantes a esta que coletamos de outras fontes de notícias.

ESKOM LIVE | Load shedding drops to Stage 3 on Monday, then more Stage 2 until further notice | BusinessESKOM LIVE | Loadshedding drops to Stage 3 on Monday, then more Stage 2 until further notice | News24_Business _Business We don't care' _Business Until Ramaphosa is out of office there will be not load shedding _Business Wiw not stage 1
Fonte: News24 - 🏆 4. / 80 Consulte Mais informação »

Murray & Roberts slumps as Australian unit enters business rescue | BusinessShares of engineering firm Murray & Roberts slumped by double digits on Monday morning, after it said its proposed R4 billion sale of its Australian business unit Clough had fallen through, resulting in a business rescue process. | News24_Business _Business Gemeente Heemstede de heer en mevrouw BIDS Schenker heeft 500K weggegooid en is niet tevreden over de zinloosheid van de ontwerpen waarom niet gewoon de OUDE BOUWMATERIALEN BOUWTEKENINGEN er bij gehaald ? Herhalen de oude Tekeningen Belvédère HeemCour
Fonte: News24 - 🏆 4. / 80 Consulte Mais informação »

Political change is also the business of businessThis past week I spent a few hours visiting an innovative South African agri-technology business that is well on its way to becoming a global player. I was blown away by the knowledge and technology they produce, and their approach to solving problems, writes Songezo Zibi.
Fonte: SundayTimesZA - 🏆 47. / 51 Consulte Mais informação »

Metair puts brakes on plan to split business amid Turkish hyperinflation, Ukraine turmoil | BusinessDespite various disruptions, vehicle component and battery manufacturer Metair is upbeat about local car output – but its battery businesses in Turkey and Romania have been hit by hyperinflation and the invasion of Ukraine. | News24_Business
Fonte: News24 - 🏆 4. / 80 Consulte Mais informação »