: The construction of Phase 1A of the Sabah Pan Borneo Highway is facing delays due to land acquisition issues and the extensive time required for utility relocation along the project alignment, said Deputy Works Minister Datuk Seri Ahmad Maslan.
“Therefore, we want to prevent this issue from arising in the implementation of Phase 1B of the Sabah LPB, where the contractor received the Letter of Acceptance just two days ago,” he said during an inspection of the Sabah LPB Package 8 project at Jalan Sepanggar-Berungis today. “Four work packages have been completed and are now open to road users, while the remaining packages are at various stages of construction. These are expected to be finished in phases by the first quarter of 2026. Phase 1A covers an estimated distance of 283 kilometres,” he said.
Business Business Latest News, Business Business Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
Source: malaymail - 🏆 1. / 86 Read more »
Source: malaymail - 🏆 1. / 86 Read more »