New data centres planned for the greater Dublin region will be denied permission to connect to the national grid, theEirgrid, the national grid operator, has told the data centre industry that it
will not be able to provide them with new connection agreements for facilities in the region until 2028 at the earliest. The move amounts to an effective ban on the development of new facilities in the...