The information includes a chart ofconstruction/improvement investments. Five currently are underway, including reconstruction of more than 18 miles of the Dallas North Tollway through Frisco.
Map of the projects indicate the project location, where the roadway starts and ends, how many lanes and miles, the estimated cost and the start and expected end date of construction. The North Texas Tollway Authority started reconstructing the DNT lanes in August 2022. Total cost of that project is $127 million, with the city of Frisco’s estimated portion estimated at $9.6 million, according to the data.Roadway congestion is a concern for residents, with many asking questions at