Company should have been charged RM116.54 million for non-delivery of warships, A-G's Report shows

  • 📰 fmtoday
  • ⏱ Reading Time:
  • 27 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 14%
  • Publisher: 72%

대한민국 뉴스 뉴스

대한민국 최근 뉴스,대한민국 헤드 라인

The report also says the defence ministry's progress payments in 2019 exceeded the actual work done on LCS 1 by 21.2%. FMTNews Warship Malaysia

A littoral combat ship similar to the ones supposed to have been delivered.

In the event of a delay of more than 12 months, it said, the defence ministry had the right to end the contract or maintain it while ensuring that the company fulfilled its obligation, with the ministry maintaining the right to claim damages in the aforementioned clause. Instead, the defence ministry only released a reminder to the company on June 14, 2019 about the delay in delivery of the warships.

The delay of 435 days as of June 10 meant that the company was supposed to pay a total of RM217.5 million in damages.

 

귀하의 의견에 감사드립니다. 귀하의 의견은 검토 후 게시됩니다.
이 소식을 빠르게 읽을 수 있도록 요약했습니다. 뉴스에 관심이 있으시면 여기에서 전문을 읽으실 수 있습니다. 더 많은 것을 읽으십시오:

 /  🏆 5. in KR

대한민국 최근 뉴스, 대한민국 헤드 라인

Similar News:다른 뉴스 소스에서 수집한 이와 유사한 뉴스 기사를 읽을 수도 있습니다.

A-G Report: Defence Ministry did not impose claims or late charges of RM116.54mil to company supposed to deliver its shipPETALING JAYA: The Defence Ministry failed to impose liquidated damages or late charges of RM116.54mil on the company that was supposed to deliver the littoral combat ship (LCS) 1, said the 2019 Auditor-General’s report.
출처: staronline - 🏆 4. / 75 더 많은 것을 읽으십시오 »

A-G Report: Defence Ministry did not impose claims or late charges of RM116.54mil to company supposed to deliver its shipPETALING JAYA: The Defence Ministry failed to impose liquidated damages or late charges of RM116.54mil on the company that was supposed to deliver the littoral combat ship (LCS) 1, said the 2019 Auditor-General’s report.
출처: staronline - 🏆 4. / 75 더 많은 것을 읽으십시오 »