DPWH to complete right-of-way acquisition for CALAX Silang Interchange in Q1

  • 📰 gmanews
  • ⏱ Reading Time:
  • 54 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 25%
  • Publisher: 68%

Malaysia News News

Malaysia Malaysia Latest News,Malaysia Malaysia Headlines

Asked when the DPWH eyes to resolve the right-of-way issues in the CALAX segment, DPWH director of public-private partnership service Alex Bote said, “[We] target to complete up to Aguinaldo is first quarter next year.”

The Department of Public Works and Highways is targeting to complete its acquisition of right-of-way for a segment of the Cavite-Laguna Expressway .

To recall, CALAX operator and developer MPCALA Holdings Inc. said the completion of CALAX Silang Interchange has been with the target date being moved several times, with the latest being December of 2022 again uncertain.Asked when the DPWH eyes to resolve the right-of-way issues in the CALAX segment, DPWH director of public-private partnership service Alex Bote said, “[We] target to complete up to Aguinaldo is first quarter next year.”

“We only have two remaining properties for acquisition, but that’s already in court for some time,” Bote said in a text message.in resolving the right-of-way issues hounding the completion of the CALAX segment.“We’re preparing a letter to the Office of Court Admin to fasttrack the acquisition process,” he added.The segment spans at 3.9 kilometers with 2x2 lane expressway from Silang East Interchange to Aguinaldo Highway in Cavite.

Upon completion, the subsection will serve more motorists given the reduced traffic situation. Current average daily traffic is 33,000 from Mamplasan to Silang East interchange.

We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

 /  🏆 11. in MY
 

Thank you for your comment. Your comment will be published after being reviewed.
Please try again later.

Malaysia Malaysia Latest News, Malaysia Malaysia Headlines