Coroner criticises traffic company's 'insulting' decision not to appear at worker death inquest

  • 📰 abcnews
  • ⏱ Reading Time:
  • 49 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 23%
  • Publisher: 83%

Malaysia News News

Malaysia Malaysia Latest News,Malaysia Malaysia Headlines

Traffic management planning was wholly inadequate on the day a road worker was struck and killed by a ute in northern Tasmania six years ago, a coroner finds.

Coroner Simon Cooper said apart from Mr Higgs's criminal inattention and speeding, a significant reason why Mr Close was killed was because he had no barrier between him and the first car approaching him.

"Numerous methods were identified to ensure that no road worker need ever to be the 'first line of defence'," Mr Cooper said. "I recommend that under no circumstances should any road worker be positioned on the road without a physical barrier between her or him and the first approaching vehicle." He said traffic management planning on the day by Altus Traffic was"wholly inadequate" and that a lack of proper planning contributed to Mr Close's death."Inadequate staff were provided for the task . No site-specific planning occurred at all. None of the workers associated with the task had the necessary qualification to enable site-specific planning to be carried out.

"The starkest example of the inadequacy of Altus's provision of traffic management was the fact that the traffic controller, Mr Close, found himself in a position where he was the 'first line of defence'."

 

Thank you for your comment. Your comment will be published after being reviewed.
Please try again later.

A fine for a workers death, Altus Traffic got of cheap

We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

 /  🏆 5. in MY

Malaysia Malaysia Latest News, Malaysia Malaysia Headlines

Similar News:You can also read news stories similar to this one that we have collected from other news sources.

Migrant workers face greater deportation risk when sponsor company collapsesIncreased waiting times for visas in Australia are seeing migrant workers being left with little time to find an alternative way of staying.
Source: SBSNews - 🏆 3. / 89 Read more »