Stefanutti Stocks confident R1.14bn claim for Kusile project ‘accurate’

  • 📰 Moneyweb
  • ⏱ Reading Time:
  • 20 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 11%
  • Publisher: 77%

Nigeria News News

Nigeria Nigeria Latest News,Nigeria Nigeria Headlines

StefanuttiStocks, which has submitted provisional claims to the total value of R1.14 billion to Eskom for work done on the Kusile Power Station project, has expressed confidence its final payment application is accurate. Moneyweb PowerSupply

JSE-listed construction group Stefanutti Stocks, which has submitted provisional claims to the total value of R1.14 billion to Eskom for work done on the Kusile Power Station project, has expressed confidence its final payment application is accurate. Stefanutti Stocks CEO Russell Crawford said on Thursday the group has therefore not made any provision for overpayment.

The group expressed confidence the termination was lawful and has therefore not made any provision for it. It added that the arbitration related to the cancellation of a petrochemical contract had to be postponed due to a fundamental change in the client’s defence and a date for the arbitration is yet to be set. “At this stage the financial impact thereof cannot be quantified,” it said.

 

Thank you for your comment. Your comment will be published after being reviewed.
Please try again later.
We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

 /  🏆 5. in NG

Nigeria Nigeria Latest News, Nigeria Nigeria Headlines