Company should have been charged RM116.54 million for non-delivery of warships, A-G's Report shows

  • 📰 fmtoday
  • ⏱ Reading Time:
  • 27 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 14%
  • Publisher: 72%

Sverige Nyheter Nyheter

Sverige Senaste nytt,Sverige Rubriker

The report also says the defence ministry's progress payments in 2019 exceeded the actual work done on LCS 1 by 21.2%. FMTNews Warship Malaysia

A littoral combat ship similar to the ones supposed to have been delivered.

In the event of a delay of more than 12 months, it said, the defence ministry had the right to end the contract or maintain it while ensuring that the company fulfilled its obligation, with the ministry maintaining the right to claim damages in the aforementioned clause. Instead, the defence ministry only released a reminder to the company on June 14, 2019 about the delay in delivery of the warships.

The delay of 435 days as of June 10 meant that the company was supposed to pay a total of RM217.5 million in damages.

Vi har sammanfattat den här nyheten så att du kan läsa den snabbt. Om du är intresserad av nyheterna kan du läsa hela texten här. Läs mer:

 /  🏆 5. in SE
 

Tack för din kommentar. Din kommentar kommer att publiceras efter att ha granskats.

Sverige Senaste nytt, Sverige Rubriker

Similar News:Du kan också läsa nyheter som liknar den här som vi har samlat in från andra nyhetskällor.

A-G Report: Defence Ministry did not impose claims or late charges of RM116.54mil to company supposed to deliver its shipPETALING JAYA: The Defence Ministry failed to impose liquidated damages or late charges of RM116.54mil on the company that was supposed to deliver the littoral combat ship (LCS) 1, said the 2019 Auditor-General’s report.
Källa: staronline - 🏆 4. / 75 Läs mer »

A-G Report: Defence Ministry did not impose claims or late charges of RM116.54mil to company supposed to deliver its shipPETALING JAYA: The Defence Ministry failed to impose liquidated damages or late charges of RM116.54mil on the company that was supposed to deliver the littoral combat ship (LCS) 1, said the 2019 Auditor-General’s report.
Källa: staronline - 🏆 4. / 75 Läs mer »