The contract encompasses civil and structural works, which are slated to start this August. Separate contracts will be called to equip the DLMs with mechanical and electrical components. Construction work is expected to complete by 2025.
The first was awarded to McConnell Dowell to carry out site development works in January 2019. A joint venture between Koh Brothers Building and Civil Engineering Contractor as well as China Harbour Engineering Co was then appointed in July 2019 to build the influent pumping stations. SembCorp Design and Construction won the third contract for the plant’s biosolids treatment facility in March 2020.
The Tuas Water Reclamation Plant is a key component of PUB’s Deep Tunnel Sewerage System Phase 2 project.