Tri-State Generation and Transmission’s largest member,
The two utilities’ dispute has played out in court and before regulators, including the Federal Energy Regulatory Commission, or FERC. “We’ve literally been waiting every day for the final FERC ruling. The administrative law judge gave us that calculator, but FERC has to give us their final stamp of approval,” said Mark Gabriel, United Power president and CEO.“But we have to go full steam ahead no matter what because we’ve got a hard and fast departure date of May 1, 2024,” Gabriel said.declined to comment on United Power’s announcement of its contract with Guzman.