Eskom tender crushes company

  • 📰 mybroadband
  • ⏱ Reading Time:
  • 27 sec. here
  • 6 min. at publisher
  • 📊 Quality Score:
  • News: 28%
  • Publisher: 67%

Eskom ニュース

Headline,Kusile,Stefanutti Stocks

Stefanutti Stocks is in financial distress, which is partly to blame on an Eskom tender to work on the Kusile power plant.

The details of the ill-fated tender were contained in Stefanutti Stocks’ results for the year ending 29 February 2024.

The company highlighted that its financial difficulty in the past few years stemmed from a 2008 Eskom tender. However, there were consistent delays in completing the Kusile project due to site access and construction problems. Due to the delays, the company incurred significant prolongation costs and approached the DAB to assess Eskom’s claims.

It is under significant debt pressure, with its total liabilities exceeding its total assets for the first time in 2022, deeming the group technically insolvent.

 

コメントありがとうございます。コメントは審査後に公開されます。
このニュースをすぐに読めるように要約しました。ニュースに興味がある場合は、ここで全文を読むことができます。 続きを読む:

 /  🏆 11. in JP

日本 最新ニュース, 日本 見出し

Similar News:他のニュース ソースから収集した、これに似たニュース記事を読むこともできます。

Stefanutti Stocks doubles operating profits, eyes Kusile closureStefanutti Stocks doubles operating profits, eyes Kusile closure
ソース: News24 - 🏆 4. / 80 続きを読む »

Stefanutti Stocks’ R1.6bn claim against Eskom expected to be resolved in Q3The group is also involved in a dispute with Eskom related to another Kusile Power Station project, Package 28.
ソース: TheCitizen_News - 🏆 6. / 75 続きを読む »

Stefanutti Stocks expects final decision on R1.6bn Eskom claim in Q3Claim relates to building contract at Kusile Power Station.
ソース: Moneyweb - 🏆 5. / 77 続きを読む »