Eskom will implement continuous stage 2 load shedding until further notice due to the breakdown of six generating units at five power stations, the power utility said on Friday afternoon.
Stage 1 will resume at 05:00 on Monday morning until 16:00, when Stage 2 will be implemented throughout Monday night. The lifeline from PetroSA was supplied after Eskom recently ran out of funds to pay for diesel, which it uses to supplement generation capacity.Since Wednesday afternoon, a generating unit each at Grootvlei, Kendal and Tutuka power stations were taken offline for repairs, Eskom said. Another four units were taken offline at Camden power station to repair a water leak on a line that supplies auxiliary cooling water.
The Department of Public Enterprises, which oversees state-owned Eskom, said earlier that it’s urgently working with National Treasury and the utility to find money for diesel. Stage 4 load shedding will be implemented continuously until 05:00 on Tuesday morning, Eskom said on Monday afternoon.Stage 4 will be implemented daily at 16:00 - 05:00 until further notice, the utility said.
Three units at Kusile Power Station are offline due to the duct failure late in October and will remain offline for a few months while repairs to the chimney system take place, it added. Meanwhile Unit 1 of Koeberg Nuclear Power Station will continue to generate at a reduced output over the next three weeks.Stage 4 load shedding was suspended at 08:00 on Sunday, power utility Eskom announced.
Since Friday morning a generating unit each at Kendal and Kriel power stations were taken offline for repairs. There have also been delays in returning to service a unit each at Arnot, Grootvlei, Hendrina and Tutuka power stations . He said those municipalities that owed Eskom needed to consider their role in causing more load shedding.
"We will do whatever is necessary to turn this around and supply electricity to the country. We have accepted this challenge."As the briefing ends - spokesperson Sikonathi Mantshantsha says Stage 3 load shedding will return on Wednesday evening. Oberholzer - we had a submission for a full-time head of generation to the previous board in Sept. They requested permission, and it was not entertained for submission to the Sept board meeting.
_Business This play of power negates the fast implementation of new Governing of South Africa for prosperity and peace .Well it's on the way before mid 2023. Don't worry be happy.
_Business Or is it because the President of South Africa survived the Phala Phala sham report so well?
_Business And the bs continues 🙄
_Business In this heat?
_Business Self inflicted breakdowns🤣🤣🤣🤣🤣to benefit certain whites and punish Blacks🤣🤣🤣🤣
_Business Well whiptidoooodaaa South Africa our land. 💀
_Business Random units breaking down once again. Lets remember we came from being told qet coal was the cause at some point. Its all BS, it always has been BS and always will be BS.
_Business Mnxim Eish Nina Nisibukelisa kakbi ibhola
_Business How the hell does 6 generating units break down at the same time? Smells like BS
_Business
_Business Thanks to cANCer
_Business 🤣🤣🤣
_Business I wonder how enormous the performance bonus de ruyter is going to give to himself ...
_Business Ag bullshit were are the proof of this so called breakdowns whe had enough of this when is it giong to end 😡😡😡😡😡😡😡😡😡
Россия Последние новости, Россия Последние новости
Similar News:Вы также можете прочитать подобные новости, которые мы собрали из других источников новостей
Источник: News24 - 🏆 4. / 80 Прочитайте больше »
Источник: TheCitizen_News - 🏆 6. / 75 Прочитайте больше »
Источник: Moneyweb - 🏆 5. / 77 Прочитайте больше »